To be held on
Monday, March 3, 2014 at 2:00 p.m. Committee Members are asked to meet
in the Council Chambers at 395 Mulock Drive, Newmarket, Ontario.
Councillor Hempen,
Chair.
NEW
BUSINESS:
1. APPLICATION FOR SITE PLAN
APPROVAL
17150 YONGE STREET - WARD 7
(NORTH SIDE OF EAGLE STREET,
WEST SIDE OF YONGE STREET)
OUR
FILE NO.: D11-NP1403
THE REGIONAL MUNICIPALITY OF YORK
Application
for Site Plan Approval to permit an 8 storey Administrative Centre Annex
Building with a gross floor area of 37,628.6 m2 together with 2
levels of underground parking and a pedestrian bridge of 137.76 m2 connecting
the proposed annex building to the main administrative building at 17250 Yonge
Street on the subject lands.
Carl
Blanchaer from WZMH Architects will be present to address the Committee.
The following
people will also be in attendance:
Region of
York:
- Jim
Davidson, Commissioner, Corporate Services, Commissioner's Office
- Rene Masad,
Director, Property Services Branch
- Martin
Silver, Manager, Capital Delivery, Property Services Branch
- Michael Del
Buono, Project Manager, Capital Delivery, Property Services Branch
- Laura Van
Vliet, Project Coordinator, Capital Delivery, Property Services Branch
AECOM
Canada Ltd.:
WZMH
Architects:
Malone
Given Parsons Ltd.:
MMM Group:
- Derek
Dagleish (Transportation)
- Ben Worth
(Civil Engineering)
Dillon
Consulting Limited:
Plans submitted: Site Survey (Drawing No. A-001 Rev. 3 dated
January 24, 2014)
Site
Plan (Drawing No. A-100 Rev. 3 dated January 24, 2014)
Demolition
Site Plan (Drawing No. A-100D Rev. 3 dated January 24, 2014)
P2
Parking Elevation Plan (Drawing No. A-200 Rev. 3 dated January 24, 2014)
P1
Parking Level Plan (Drawing No. A-201 Rev. 3 dated January 24, 2014)
Ground
Floor Plan (Drawing No. A-202 Rev. 3 dated January 24, 2014)
Second
Floor Plan (Drawing No. A-203 Rev. 3 dated January 24, 2014)
Third
Floor Plan (Drawing No. A-204 Rev. 3 dated January 24, 2014)
Fourth
Floor Plan (Drawing No. A-205 Rev. 3 dated January 24, 2014)
Fifth,
Sixth, Seventh & Eighth Floor Plan (Drawing No. A-206 Rev. 3 dated January
24, 2014)
Penthouse
Floor Plan (Drawing No. A-207 Rev. 3 dated January 24, 2014)
Roof
Plan (Drawing No. A-208 Rev. 3 dated January 24, 2014)
Tree
Protection Plan (Drawing No. L-200 Rev. 3 dated January 24, 2014)
Landscape
Plan (Drawing No. L-201 Rev. 3 dated January 24, 2014)
Landscape
Plan & Sections (Drawing No. L-202 Rev. 3 dated January 24, 2014)
Landscape
Planting Plan (Drawing No. L-203 Rev. 3 dated January 24, 2014)
Landscape
Planting Plan (Drawing No. L-204 Rev. 3 dated January 24, 2014)
Landscape
Details (Drawing No. L-210 Rev. 3 dated January 24, 2014)
North
Elevation (Drawing No. A-400 Rev. 3 dated January 24, 2014)
South
Elevation (Drawing No. A-401 Rev. 3 dated January 24, 2014)
East
Elevation (Drawing No. A-402 Rev. 3 dated January 24, 2014)
West
Elevation (Drawing No. A-403 Rev. 3 dated January 24, 2014)
Courtyard
Building Elevations (Drawing No. A-404 Rev. 3 dated January 24, 2014)
Building
Sections (Drawing No. A-410 Rev. 3 dated January 24, 2014)
Building
Sections (Drawing No. A-411 Rev. 3 dated January 24, 2014)
Surveyor’s
Real Property Report – Sheet 1 dated June 10, 1999, prepared by Lloyd &
Purcell Ltd., Ontario Land Surveyors
Documents
attached: GIS
photograph overlay maps
Site Plan
Accessibility Checklist
Yonge-Davis
Development Standards Checklist, together with letter from Len Abelman of WZMH
Architects dated February 11, 2014
Colour
Rendering – Aerial View From East
Review Notes